Free Web Hosting by Netfirms
Web Hosting by Netfirms | Free Domain Names by Netfirms

Tenders Report of the Country Projects

 

Country-Plan Projects and Tenders

580 مليون جنيه تمويل أجنبي لتحديث 12 تربين للسد العالي

German Bank for Reconstruction extending finance to back the foreign currency component of L.E. 580 million project for the revamping of 12 of the High Dam turbines.

Sunday, November 13, 2005
Al-Akhbar
Asswan
German Bank for Reconstruction has extended finance to back the foreign currency component of L.E. 580 million project for the revamping of 12 of the High Dam turbines. Project is for completion in 82 months at a rate of two turbines each 12 months. Project aims at extending the productive life of Egypt largest hydroelectric power station.

Beneficiary Sectors
-
Electromechanical Works
      Electromechanical Works
-
Energy
      Generation
-
Information Technology & Telecom
      Automation & Process Control