25 مليون جنيه لإنارة 44 كم من الطريق السويس القاهرة L.E. 25 million project announced for the lighting of 44 Km long section of Suez/ Cairo desert road. |
| Date Published | Monday, December 19, 2005 |
| Source Name | Al-Ahram |
| Location Name | Suez |
|
Description Date Format: (mm/dd/yyyy) |
L.E. 25 million project announced for
the lighting of 44 Km long section of Suez/ Cairo desert road. Project
finance is raised by the Ministry of Defense, the Ministry of
Transport & Suez Governorate. Suez Governorate Deputy Secretary
General Mr. Alaa Bodour said the project is scheduled for completion
in 3 years. (N.B.) Development sends good news for a long list of
lighting equipment suppliers & related feeder industries). Above
figures show an average lighting cost per one kilometer of almost L.E.
570,000. |
| Sectors Section |
Beneficiary Sectors - Energy Lighting Equipment & Works - Industry Electrical Feeder Industries |